Construction updates from Market & Johnson…

Work performed in the last 30 days

  • Continued Drilling Geothermal Wells
  • Completed OH and In-Wall Rough-ins on 1st Floor and 2nd Floor
  • Continued OH and In-Wall Rough-ins on Lower Level
  • Completed Soffit framing 2nd Floor, 1st Floor and Lower level
  • Formed & Poured Foundation for Elevator and Lay Back for New Elevator Shaft
  • Framed Parapet on Existing Roof
  • Re-Roofed Existing 1st and 2nd Floor Roofs
  • Installed New Roof on the 3rd Floor Addition
  • Framed and Sheet Exterior Walls on 3rd Floor
  • Started Setting Overhead Hangers on 3rd Floor
  • Completed Fireproof 3rd Floor Addition Steel
  • Prepped for Slab Placement at 3rd Floor Addition

Schedule

Geo-Thermal Wells Complete … November 5, 2021
Install New Elevator … December 6, 2021
Building Enclosed … December 31, 2021
Final Occupancy … July 1, 2022

Work scheduled for the next 30 days

  • Complete Drilling Geothermal Wells on Eau Claire Street
  • Install Geothermal Lines from Geo Wells on Eau Claire Street to the Building
  • Install Storm Lines on Eau Claire Street
  • Begin Work on US Bank Entry/Exit Drives
  • Install 2nd Floor and 1st Floor Door Frames
  • Fireproof 3rd Floor Addition
  • Pour Slab-on-Grade on 3rd Floor
  • Frame Interior Walls on 3rd Floor
  • Continue Selective MEP Rough-Ins on All Floors
  • Install Both Air Handler Units on 2nd Floor and Lower Level
  • Install 1st and 2nd Floor Drywall on Soffits and Tops of Walls
  • Install New Electrical and Water Service

Photos by Market & Johnson (October)


Drone Flyover by Market & Johnson (October)


We’re almost there!

Help us cross the fundraising finish line. Donate today!

See donation options…