Construction updates from Market & Johnson…

Work performed in the last 30 days

  • Completed Drilling Geothermal Wells on Eau Claire Street
  • Installed New Water Service to building from Dewey Street
  • Installed 1st and 2nd Floor Drywall on Soffits and Tops of Walls
  • Continued Selective MEP Rough-Ins on All Floors
  • Began installing drywall level 2.
  • Began Tape and Finish Level 2
  • Installed Air Handler Units on 2nd Floor and Lower Level
  • Completed Soffit Framing All Floors
  • Completed Masonry Elevator Shaft
  • Installed Headwaters Bridge Steel and Decking
  • Received and Installed 2nd Floor and 1st Floor Door Frames
  • Fireproofed 3rd Floor Addition
  • Poured Slab-on-Grade on 3rd Floor
  • Installed 3rd Floor Interior Walls
  • Began 3rd floor MEPF OH Rough-Ins

Schedule

Begin Elevator Install … December 6, 2021
Building Enclosed … December 31, 2021
Begin Concrete Polishing … January 24, 2022
Final Occupancy … July 1, 2022

Work scheduled for the next 30 days

  • Install Geothermal Lines from Geo Wells on Eau Claire Street to the Building
  • Install Storm Lines on Eau Claire Street
  • Install New Electrical Service and Switch Gear in coordination with Xcel Energy
  • Complete Roofing All Levels
  • Begin Install Metal Panel System at 3rd Floor Roof
  • Complete Selective Overhead/In-Wall MEP Work on All Floors
  • Install Drywall Ceilings on All Floors
  • Install Drywall on all floors
  • Tape, Finish, and Paint 1st and 2nd Floor
  • Install New Duct on Lower Level
  • Install Drywall Tops and Frame Ceilings on 3rd Floor
  • Begin install of New Elevator
  • Mock-Up Polished Concrete Floors
  • Review Casework/Millwork Shop Drawings

Photos by Market & Johnson (November)


Drone Flyover by Market & Johnson (November)


We’re almost there!

Help us cross the fundraising finish line. Donate today!

See donation options…