Construction updates from Market & Johnson…
Work performed in the last 30 days
Building
- Completed Ceramic Floor Tile 3rd, 2nd and 1st Floors and Installing Tile lower Level
- Complete Above Ceiling Inspections and Dropped Ceiling Tile
- Poured Headwaters Bridge
- Fireproofed headwaters Bridge
- Installed Bathroom Fixtures and Decorative Wood Ceiling
- Installed Doors and Hardware
- Began Installing Specialties and Caulking Exterior Brick
- Began Washing Exterior Brick and Retaining Wall
- Completed Metal Panels
- Installed Terrance Handrail
- Began Install Metal Roof Coping Cap
Courtyard/Plaza
- Demoed Existing Courtyard Finishes
- Installed Storm Courtyard Area, Bollards and Site Walls Courtyard
- Installed Curb & Gutter Courtyard
- Began Storm at Plaza Area and Excavations for Retaining Walls Plaza
Schedule
Final Occupancy … July 1, 2022
Furniture Install Begins … July 5, 2022
Work scheduled for the next 30 days
Building
- Complete Casework Install and Countertop Install
- Install Terrazzo Flooring at Entry
- Install Carpet and Soft Flooring All Levels
- Complete Window Blinds, Bathroom Fixtures, and Painting
- Complete Dropping Ceiling Tiles
- Install Living Roofs and Paver Systems as Growing Season Allows
- Begin Flushing and Filling Mechanical System
- Begin Start-ups of Mechanical System
- Final Clean Building and Clean Windows
- M&J Work to Complete List in Preparation for MSR Punchlist
Courtyard/Plaza
- Pour Sidewalks Courtyard Area
- Begin Installing Specialties in Courtyard
- Install Curb & Gutter Plaza Area
- Install Site walls and sculpture pads Plaza Area
- Mobilize Irrigation and Landscaping
- Prep for Asphalt