Construction updates from Market & Johnson…

Work performed in the last 5 days

  • Started Abatement
  • Started to Salvage Wood Paneling on 2nd Floor
  • Started to Demo 1st and 2nd Floor Casework
  • Started to Demo 1st Floor Carpet Tile
  • Started to Demo Electrical Outlets and Lights
  • Set up Temporary Power
  • Continue to Work Through Shop Drawings/Submittals

Work scheduled for the next 5 days

  • Continue Abatement
  • Continue to Salvage Wood Paneling on 2nd Floor
  • Continue to Demo 1st and 2nd Floor Casework
  • Continue to Demo 1st Floor Carpet Tile
  • Continue to Demo Lights
  • Start to Demo HVAC
  • Continue to Work Through Shop Drawings/Submittals

Photos by Market & Johnson (May)