Construction updates from Market & Johnson…
Work performed in the last 30 days
- Installed New Electrical Service and Switch Gear in coordination with Xcel Energy
- Installed Book Conveyor
- Completed Roofing All Levels
- Completed Tape, Finish, and Paint on 1st and 3rd Floors
- Installed Ceiling Grid on 1st level
- Continued Ceiling trim out on 2nd floor
- Completed 2nd floor concrete polishing
- Began concrete floor polishing 1st floor
- Continued Curtain Walls on 1st and 3rd Floor
- Continued Installing the Metal Panel System on the 3rd Floor Addition
- Continued OH MEPF Rough-in on 3rd Floor
- Completed Lower Level OH MEPF Rough-In
- Installed Light Fixtures as Available
Schedule
Xcel Power Service Switchover … March 3, 2022
Begin Casework Install … April 1, 2022
Final Occupancy … July 1, 2022
Work scheduled for the next 30 days
- Complete Power Switchover/Service Upgrade
- Complete Concrete Polishing First Floor
- Complete Tape, Finish and Paint on 3rd Floor
- Complete Tape, Finish and Paint on Lower Level
- Complete Installation of 3rd Floor Curtain Walls
- Begin Installing Guardrail at Stairs and Headwaters Area
- Begin Ceramic Tile Install in Restrooms
- Begin Fluid Applied Flooring Install
- Install Ceiling Grid Lower Level
- Continue Installing the Metal Panel System on the 3rd Floor Addition
- Begin Concrete Polishing 3rd Floor
- Receive Casework Delivery