Construction updates from Market & Johnson

Work performed in the last 30 days

  • Installed New Electrical Service and Switch Gear in coordination with Xcel Energy
  • Installed Book Conveyor
  • Completed Roofing All Levels
  • Completed Tape, Finish, and Paint on 1st and 3rd Floors
  • Installed Ceiling Grid on 1st level
  • Continued Ceiling trim out on 2nd floor
  • Completed 2nd floor concrete polishing
  • Began concrete floor polishing 1st floor
  • Continued Curtain Walls on 1st and 3rd Floor
  • Continued Installing the Metal Panel System on the 3rd Floor Addition
  • Continued OH MEPF Rough-in on 3rd Floor
  • Completed Lower Level OH MEPF Rough-In
  • Installed Light Fixtures as Available

Schedule

Xcel Power Service Switchover … March 3, 2022
Begin Casework Install … April 1, 2022
Final Occupancy … July 1, 2022

Work scheduled for the next 30 days

  • Complete Power Switchover/Service Upgrade
  • Complete Concrete Polishing First Floor
  • Complete Tape, Finish and Paint on 3rd Floor
  • Complete Tape, Finish and Paint on Lower Level
  • Complete Installation of 3rd Floor Curtain Walls
  • Begin Installing Guardrail at Stairs and Headwaters Area
  • Begin Ceramic Tile Install in Restrooms
  • Begin Fluid Applied Flooring Install
  • Install Ceiling Grid Lower Level
  • Continue Installing the Metal Panel System on the 3rd Floor Addition
  • Begin Concrete Polishing 3rd Floor
  • Receive Casework Delivery

Photos by Market & Johnson (March)


Drone Flyover by Market & Johnson (March)


We’re almost there!