Construction updates from Market & Johnson…
Work performed in the last 30 days
Building
- Completed Install of Glass Doors and Storefronts
- Completed Install of Specialties on all Floors
- Completed Install of Terrazzo
- Completed Install of Flooring
- Completed Fire Alarm, Elevator, and Occupancy Inspections
- Started to Install Shelving
Courtyard/Plaza
- Installed Site walls and sculpture pads Plaza Area
- Installed Irrigation and Landscaping
- Installed Asphalt
- Installed Storm and Site Utilities
- Installed Front Entry Tree Grates and Pavers
- Started to Pave Sidewalks in Plaza Area
Schedule
Begin Install of Book Conveyor System … August 8, 2022
Library Begins to Move In … August 8, 2022
Library Open for Business … September 2022
Work scheduled for the next 30 days
Building
- Complete Installing Lighting Equipment
- Complete Commissioning Functional Checklist
- Complete All Punch List Items
- Install AV Systems
- Final Install of the Book Conveyor System
- Start Installing Furniture
Courtyard/Plaza
- Complete Installing Specialties in Courtyard
- Finish all Exterior Concrete Work
- Finish all Exterior Lighting
- Finish Storm and Site Utilities
- Finish Landscaping and Irrigation
- Install Finial Layer of Asphalt in the Lower Level
Photos by Market & Johnson (July)




