Work performed in the last 30 days

  • Completed Abatement
  • Demoed 2nd Floor Walls
  • Completed 2nd Floor Demo
  • X-Ray for PT Tendons on 2nd Level
  • Installed Scaffold Work Platform at Headwaters
  • Demoed 1st Floor and Lower-Level Plumbing
  • Demoed 1st Floor HVAC and Lower-Level Lights
  • Demoed 1st Floor and Lower-Level Ceiling
  • Demoed 1st Floor Electrical Wall-ins and Walls
  • Demo Lower Level Ceilings and Lower Level Lights
  • Coordinated with City of Eau Claire and US Bank on Geo-Well Install
  • Surveyed Geo-Well Locations
  • Continued to Work Through Shop Drawings and Submittals

Facts

  • Demoed and Recycled 40 Tons of Metal
  • Demoed 90 Tons of Demolition Material
  • Demoed and Recycled 25 Tons of Masonry Demo

Work scheduled for the next 30 days

  • Demo Lower-Level HVAC and Walls
  • Complete All Floors Wall Layout
  • Continue X-Raying existing structure as needed.
  • Begin Framing Walls 2nd Level.
  • Demo Existing Elevator and Dumb Waiter
  • Demo Roof and Parapet Walls for 3rd floor Addition
  • Demo Structures at Existing 2nd Floor Room
  • Demo and Prep New Masonry for New Openings
  • Start Lower-Level Underground Plumbing
  • Begin Site Work and Utilities
  • Prep for Geo-Thermal Well Installation
  • Continue to Work Through Shop Drawings and Submittals

Schedule

Demo Complete … July 30, 2021
Structural Steel Install … August 16, 2021
Occupancy Inspection … July 1, 2022


Photos by Market & Johnson (July)