Construction updates from Market & Johnson…
Work performed in the last 30 days
- Tested and Flushed Geothermal System to Building
- Began Installing the Metal Panel System on the 3rd Floor Addition
- Continued Selective Overhead/In-Wall MEP Work on All Floors
- Continued Installing Drywall Ceilings on All Floors
- Completed Taping and Finishing 2nd Floor
- Continued MEPF OH Rough-in Lower Level and 3rd Floor
- Installed Ceiling Grid Level 2
- Completed New Elevator Install
- Polished Concrete Floors Level 2
Schedule
Install Book Conveyor … February 14, 2022
Begin Flooring Install … March 1, 2022
Final Occupancy … July 1, 2022
Work scheduled for the next 30 days
- Install New Electrical Service and Switch Gear in Coordination with Xcel Energy (Pending Xcel)
- Install Book Conveyor
- Complete Roofing All Levels
- Complete Tape, Finish, and Paint on 1st Floor
- Continue Tape, Finish and Paint on 3rd Floor
- Install Ceiling Grid on 1st and Lower level
- Continue Ceiling Trim out on 2nd floor
- Complete 2nd Floor Concrete Polishing
- Begin Concrete Floor Polishing 1st Floor
- Continue Curtain Walls on 1st and 3rd Floor
- Continue Installing the Metal Panel System on the 3rd Floor Addition
- Continue OH MEPF Rough-In on 3rd Floor
- Complete Lower Level OH MEPF Rough-In
- Install Light fixtures as Available
Photos by Market & Johnson (January)