Construction updates from Market & Johnson

Work performed in the last 30 days

  • Tested and Flushed Geothermal System to Building
  • Began Installing the Metal Panel System on the 3rd Floor Addition
  • Continued Selective Overhead/In-Wall MEP Work on All Floors
  • Continued Installing Drywall Ceilings on All Floors
  • Completed Taping and Finishing 2nd Floor
  • Continued MEPF OH Rough-in Lower Level and 3rd Floor
  • Installed Ceiling Grid Level 2
  • Completed New Elevator Install
  • Polished Concrete Floors Level 2

Schedule

Install Book Conveyor … February 14, 2022
Begin Flooring Install … March 1, 2022
Final Occupancy … July 1, 2022

Work scheduled for the next 30 days

  • Install New Electrical Service and Switch Gear in Coordination with Xcel Energy (Pending Xcel)
  • Install Book Conveyor
  • Complete Roofing All Levels
  • Complete Tape, Finish, and Paint on 1st Floor
  • Continue Tape, Finish and Paint on 3rd Floor
  • Install Ceiling Grid on 1st and Lower level
  • Continue Ceiling Trim out on 2nd floor
  • Complete 2nd Floor Concrete Polishing
  • Begin Concrete Floor Polishing 1st Floor
  • Continue Curtain Walls on 1st and 3rd Floor
  • Continue Installing the Metal Panel System on the 3rd Floor Addition
  • Continue OH MEPF Rough-In on 3rd Floor
  • Complete Lower Level OH MEPF Rough-In
  • Install Light fixtures as Available

Photos by Market & Johnson (January)


Drone Flyover by Market & Johnson (January)


We’re almost there!