Work performed in the last 30 days

  • Installed Geothermal Lines from Geo Wells on Eau Claire Street to the Building
  • Began Installing the Metal Panel System on the 3rd Floor Addition
  • Continued Selective Overhead/In-Wall MEP Work on All Floors
  • Began Installing Drywall Ceilings on All Floors
  • Install Drywall on all floors
  • Began Tapping Drywall on 1st and 2nd Floor
  • Began Install of New Duct on Lower Level
  • Began Installing Drywall Tops and Framing Ceilings on 3rd Floor
  • Began Install of New Elevator
  • Installed Circuit Branch Wire on 1st and 2nd Floor
  • Began Installing Low Voltage Wire 1st and 2nd Floor
  • Mocked-Up Polished Concrete Floors and Metal Panels

Schedule

Begin Concrete Polishing … January 24, 2022
Begin Flooring Install … March 1, 2022
Final Occupancy … July 1, 2022

Work scheduled for the next 30 days

  • Install New Electrical Service and Switch Gear in coordination with Xcel Energy
  • Complete Roofing All Levels
  • Complete Tape, Finish, and Paint on 1st and 2nd Floor
  • Tape, Finish and Paint on Lower Level and 3rd Floor
  • Finish Installing New Elevator
  • Install Ceiling Grid on 1st through 3rd Floors
  • Start Ceiling Trim Out
  • Begin Concrete Polishing on 2nd Floor
  • Install Curtain Walls on 1st and 3rd Floor
  • Continue Installing the Metal Panel System on the 3rd Floor Addition
  • Complete Pulling Circuit Branch and Low Voltage Wire on All Floors

Photos by Market & Johnson (December)