Construction updates from Market & Johnson

Work performed in the last 30 days

  • Completed Power Switchover/Service Upgrade
  • Completed Concrete Polishing First Floor
  • Completed Tape, Finish and Paint on 3rd Floor
  • Completed Tape, Finish and Paint on Lower Level
  • Completed Installation of 3rd Floor Curtain Walls
  • Began Installing Guardrail at Stairs and Headwaters Area
  • Began Ceramic Tile Install in Restrooms and Fluid Applied Flooring Install
  • Continued Installing the Metal Panel System on the 3rd Floor Addition
  • Began Concrete Polishing 3rd Floor
  • Receive Casework Delivery
  • Received Wood Door Delivery
  • Began Installing Carpet in Offices
  • Began Casework Install
  • Install Interior Glazing

Schedule

Pour Headwaters Bridge … April 15, 2022
Begin Exterior Plaza and Courtyard Finishes … April 18, 2022
Final Occupancy … July 1, 2022

Work scheduled for the next 30 days

  • Complete Ceramic Floor Tile 3rd, 2nd and 1st Floors
  • Begin Installing Tile lower Level
  • Pour Headwaters Bridge
  • Fireproof headwaters Bridge
  • Install Bathroom Fixtures
  • Install Decorative Wood Ceiling
  • Install Doors and Hardware
  • Begin Installing Specialties
  • Begin Courtyard and Plaza Work
  • Begin Caulking Exterior Brick, Washing Exterior Brick and Retaining Wall
  • Complete Metal Panels
  • Install Terrance Handrail
  • Install Metal Roof Coping Cap
  • Begin Roof Paver Install