Construction updates from Market & Johnson…
Work performed in the last 30 days
Building
- Completed Casework Install and Countertop Install
- Began Installing Terrazzo Flooring at Entry and Headwaters
- Installed Carpet and Soft Flooring All Levels
- Completed Bathroom Fixtures and Painting
- Completed Dropping Ceiling Tiles
- Began Installing Living Roofs and Paver Systems as Growing Season Allows
- Flushed and Filled Mechanical System
- Begin Start-ups of Mechanical System
- Final Cleaning of 3rd and 2nd Floors and Cleaned Windows
- M&J Work to Complete List on 3rd and 2nd Floors in Preparation for MSR Punchlist
- Complete Commissioning Checklists/Controls
Courtyard/Plaza
- Poured Sidewalks Along Farewell Street
- Begin Installing Specialties in Courtyard
- Install Curb & Gutter Plaza Area
- Install Site walls and sculpture pads Plaza Area
- Prep for Asphalt
Schedule
Final Occupancy … July 1, 2022
Furniture Install Begins … July 5, 2022
Work scheduled for the next 30 days
Building
- Complete Installing Lighting Equipment
- Complete Installing Glass Doors and Storefronts
- Complete Installing Specialties on all Floors
- Complete Installing Terrazzo
- Complete Paint Touch Ups on All Floors
- Complete Install of Flooring
- Complete Fire Alarm, Elevator, and Occupancy Inspections
- Complete All Punch List Items
- Start Installing Furniture
Courtyard/Plaza
- Begin Installing Specialties in Courtyard
- Install Site walls and sculpture pads Plaza Area
- Install Irrigation and Landscaping
- Install Asphalt
- Install Storm and Site Utilities