Construction updates from Market & Johnson

Work performed in the last 30 days

Building

  • Completed Casework Install and Countertop Install
  • Began Installing Terrazzo Flooring at Entry and Headwaters
  • Installed Carpet and Soft Flooring All Levels
  • Completed Bathroom Fixtures and Painting
  • Completed Dropping Ceiling Tiles
  • Began Installing Living Roofs and Paver Systems as Growing Season Allows
  • Flushed and Filled Mechanical System
  • Begin Start-ups of Mechanical System
  • Final Cleaning of 3rd and 2nd Floors and Cleaned Windows
  • M&J Work to Complete List on 3rd and 2nd Floors in Preparation for MSR Punchlist
  • Complete Commissioning Checklists/Controls

Courtyard/Plaza

  • Poured Sidewalks Along Farewell Street
  • Begin Installing Specialties in Courtyard
  • Install Curb & Gutter Plaza Area
  • Install Site walls and sculpture pads Plaza Area
  • Prep for Asphalt

Schedule

Final Occupancy … July 1, 2022
Furniture Install Begins … July 5, 2022

Work scheduled for the next 30 days

Building

  • Complete Installing Lighting Equipment
  • Complete Installing Glass Doors and Storefronts
  • Complete Installing Specialties on all Floors
  • Complete Installing Terrazzo
  • Complete Paint Touch Ups on All Floors
  • Complete Install of Flooring
  • Complete Fire Alarm, Elevator, and Occupancy Inspections
  • Complete All Punch List Items
  • Start Installing Furniture

Courtyard/Plaza

  • Begin Installing Specialties in Courtyard
  • Install Site walls and sculpture pads Plaza Area
  • Install Irrigation and Landscaping
  • Install Asphalt
  • Install Storm and Site Utilities

Photos by Market & Johnson (June)


Drone Flyover by Market & Johnson (June)


We’re almost there!