Construction updates from Market & Johnson

Work performed in the last 30 days

Building

  • Completed Ceramic Floor Tile 3rd, 2nd and 1st Floors and Installing Tile lower Level
  • Complete Above Ceiling Inspections and Dropped Ceiling Tile
  • Poured Headwaters Bridge
  • Fireproofed headwaters Bridge
  • Installed Bathroom Fixtures and Decorative Wood Ceiling
  • Installed Doors and Hardware
  • Began Installing Specialties and Caulking Exterior Brick
  • Began Washing Exterior Brick and Retaining Wall
  • Completed Metal Panels
  • Installed Terrance Handrail
  • Began Install Metal Roof Coping Cap

Courtyard/Plaza

  • Demoed Existing Courtyard Finishes
  • Installed Storm Courtyard Area, Bollards and Site Walls Courtyard
  • Installed Curb & Gutter Courtyard
  • Began Storm at Plaza Area and Excavations for Retaining Walls Plaza

Schedule

Final Occupancy … July 1, 2022
Furniture Install Begins … July 5, 2022

Work scheduled for the next 30 days

Building

  • Complete Casework Install and Countertop Install
  • Install Terrazzo Flooring at Entry
  • Install Carpet and Soft Flooring All Levels
  • Complete Window Blinds, Bathroom Fixtures, and Painting
  • Complete Dropping Ceiling Tiles
  • Install Living Roofs and Paver Systems as Growing Season Allows
  • Begin Flushing and Filling Mechanical System
  • Begin Start-ups of Mechanical System
  • Final Clean Building and Clean Windows
  • M&J Work to Complete List in Preparation for MSR Punchlist

Courtyard/Plaza

  • Pour Sidewalks Courtyard Area
  • Begin Installing Specialties in Courtyard
  • Install Curb & Gutter Plaza Area
  • Install Site walls and sculpture pads Plaza Area
  • Mobilize Irrigation and Landscaping
  • Prep for Asphalt

Photos by Market & Johnson (May)


Drone Flyover by Market & Johnson (May)


We’re almost there!