Construction updates from Market & Johnson…
Work performed in the last 30 days
- Completed Power Switchover/Service Upgrade
- Completed Concrete Polishing First Floor
- Completed Tape, Finish and Paint on 3rd Floor
- Completed Tape, Finish and Paint on Lower Level
- Completed Installation of 3rd Floor Curtain Walls
- Began Installing Guardrail at Stairs and Headwaters Area
- Began Ceramic Tile Install in Restrooms and Fluid Applied Flooring Install
- Continued Installing the Metal Panel System on the 3rd Floor Addition
- Began Concrete Polishing 3rd Floor
- Receive Casework Delivery
- Received Wood Door Delivery
- Began Installing Carpet in Offices
- Began Casework Install
- Install Interior Glazing
Schedule
Pour Headwaters Bridge … April 15, 2022
Begin Exterior Plaza and Courtyard Finishes … April 18, 2022
Final Occupancy … July 1, 2022
Work scheduled for the next 30 days
- Complete Ceramic Floor Tile 3rd, 2nd and 1st Floors
- Begin Installing Tile lower Level
- Pour Headwaters Bridge
- Fireproof headwaters Bridge
- Install Bathroom Fixtures
- Install Decorative Wood Ceiling
- Install Doors and Hardware
- Begin Installing Specialties
- Begin Courtyard and Plaza Work
- Begin Caulking Exterior Brick, Washing Exterior Brick and Retaining Wall
- Complete Metal Panels
- Install Terrance Handrail
- Install Metal Roof Coping Cap
- Begin Roof Paver Install
Photos by Market & Johnson (April)