Construction updates from Market & Johnson…
Work performed in the last 30 days
- Installed Geothermal Lines from Geo Wells on Eau Claire Street to the Building
- Began Installing the Metal Panel System on the 3rd Floor Addition
- Continued Selective Overhead/In-Wall MEP Work on All Floors
- Began Installing Drywall Ceilings on All Floors
- Install Drywall on all floors
- Began Tapping Drywall on 1st and 2nd Floor
- Began Install of New Duct on Lower Level
- Began Installing Drywall Tops and Framing Ceilings on 3rd Floor
- Began Install of New Elevator
- Installed Circuit Branch Wire on 1st and 2nd Floor
- Began Installing Low Voltage Wire 1st and 2nd Floor
- Mocked-Up Polished Concrete Floors and Metal Panels
Schedule
Begin Concrete Polishing … January 24, 2022
Begin Flooring Install … March 1, 2022
Final Occupancy … July 1, 2022
Work scheduled for the next 30 days
- Install New Electrical Service and Switch Gear in coordination with Xcel Energy
- Complete Roofing All Levels
- Complete Tape, Finish, and Paint on 1st and 2nd Floor
- Tape, Finish and Paint on Lower Level and 3rd Floor
- Finish Installing New Elevator
- Install Ceiling Grid on 1st through 3rd Floors
- Start Ceiling Trim Out
- Begin Concrete Polishing on 2nd Floor
- Install Curtain Walls on 1st and 3rd Floor
- Continue Installing the Metal Panel System on the 3rd Floor Addition
- Complete Pulling Circuit Branch and Low Voltage Wire on All Floors