Construction updates from Market & Johnson…

Work performed in the last 30 days

  • Continued Site Work in Eau Claire Street
  • Continued Drilling Geothermal Wells
  • Demo Existing Elevator Shaft
  • Demo Existing Stair to Future 3rd Level
  • Continued OH and In-Wall Rough-ins on 2nd Floor
  • Completed Interior Wall Framing on 2nd Floor, 1st Floor, and Lower Level
  • Begin Soffit framing 2nd Floor, 1st Floor and Lower level
  • Began All Trade’s Rough ins on 1st Floor
  • Began All Trade’s Rough ins on Lower Floor
  • Set and Detail Steel and Deck for Roof Addition
  • Saw Cut for New Skylights Through Existing Deck
  • Began to Install Storm Drains and Piping
  • Began Demoing 1st Floor Roofs

Schedule

Geo-Thermal Wells Complete … November 5, 2021
Begin Drywall Install … November 8, 2021
Install New Elevator … December 6, 2021
Building Enclosed … December 31, 2021
Final Occupancy … July 1, 2022

Work scheduled for the next 30 days

  • Continue Site Work in Eau Claire Street
  • Continue Drilling Geothermal Wells
  • Begin Work on US Bank Entry/Exit Drives
  • Complete OH and In-Wall Rough-ins on 1st Floor and 2nd Floor
  • Continue OH and In-Wall Rough-ins on Lower Level
  • Complete Soffit framing 2nd Floor, 1st Floor and Lower level
  • Install 2nd Floor and 1st Floor Door Frames
  • Form & Pour Foundation for Elevator and Lay Back for New Elevator Shaft
  • Frame Parapet on Existing Roof
  • Re-Roof Existing 1st and 2nd Floor Roofs
  • Complete Roofing at 3rd floor Addition
  • Frame and Sheet Exterior Walls on 3rd Floor
  • Start Setting Overhead Hangers on 3rd Floor
  • Complete Fireproof 3rd Floor Addition Steel
  • Prep for Slab Placement at 3rd Floor Addition