Construction updates from Market & Johnson…
Work performed in the last 30 days
- Continued Site Work in Eau Claire Street
- Continued Drilling Geothermal Wells
- Demo Existing Elevator Shaft
- Demo Existing Stair to Future 3rd Level
- Continued OH and In-Wall Rough-ins on 2nd Floor
- Completed Interior Wall Framing on 2nd Floor, 1st Floor, and Lower Level
- Begin Soffit framing 2nd Floor, 1st Floor and Lower level
- Began All Trade’s Rough ins on 1st Floor
- Began All Trade’s Rough ins on Lower Floor
- Set and Detail Steel and Deck for Roof Addition
- Saw Cut for New Skylights Through Existing Deck
- Began to Install Storm Drains and Piping
- Began Demoing 1st Floor Roofs
Schedule
Geo-Thermal Wells Complete … November 5, 2021
Begin Drywall Install … November 8, 2021
Install New Elevator … December 6, 2021
Building Enclosed … December 31, 2021
Final Occupancy … July 1, 2022
Work scheduled for the next 30 days
- Continue Site Work in Eau Claire Street
- Continue Drilling Geothermal Wells
- Begin Work on US Bank Entry/Exit Drives
- Complete OH and In-Wall Rough-ins on 1st Floor and 2nd Floor
- Continue OH and In-Wall Rough-ins on Lower Level
- Complete Soffit framing 2nd Floor, 1st Floor and Lower level
- Install 2nd Floor and 1st Floor Door Frames
- Form & Pour Foundation for Elevator and Lay Back for New Elevator Shaft
- Frame Parapet on Existing Roof
- Re-Roof Existing 1st and 2nd Floor Roofs
- Complete Roofing at 3rd floor Addition
- Frame and Sheet Exterior Walls on 3rd Floor
- Start Setting Overhead Hangers on 3rd Floor
- Complete Fireproof 3rd Floor Addition Steel
- Prep for Slab Placement at 3rd Floor Addition