Construction updates from Market & Johnson…

Work performed in the last 30 days

  • Demoed Elevator and Dumb Waiter
  • Demo Roof Structures and Roof for Addition
  • Complete Lower-Level Demo
  • Began X-Ray and Coring PT Slabs
  • Demo Elevator Shaft
  • Demoed 40 Tons of Metal and 55 Tons of Miscellaneous Demo
  • Demoed 130 Tons of Masonry Demo
  • Began Site Work and Removals in Eau Claire Street
  • Relocate Water and Sanitary to US Bank
  • Began Drilling Geothermal Wells
  • Began Lower-Level Underground Plumbing
  • Began All Trade’s Overhead Rough Ins on 2nd Floor
  • Began Framing 1st and 2nd Floor Walls
  • Continued to Work Through Shop Drawings and Submittals

Schedule

Structural Steel Install Begins … September 6, 2021
Building Enclosed … December 31, 2021
Install New Elevator … November 15, 2021
Occupancy Inspection … July 1, 2022

Work scheduled for the next 30 days

  • Continue Site Work in Eau Claire Street
  • Continue Drilling Geothermal Wells
  • Complete OH and In-Wall Rough Ins on 2nd Floor
  • Complete Framing 2nd Level
  • Complete Framing 1st level
  • Begin Framing Lower-Level Walls
  • Begin All Trade’s Rough Ins on 1st Floor
  • Begin All Trade’s Rough Ins on Lower Floor
  • Set and Detail Steel and Deck for Roof Addition
  • Pour Curbs on Roof
  • Core Drilling in 1st and 2nd Bathrooms for Plumbing Fixtures
  • Build Back Elevator Pit
  • Begin Roofing at Existing Building
  • Continue to Work Through Shop Drawings and Submittals

Photos by Market & Johnson (August)


Drone Flyover by Market & Johnson (August)


We’re almost there!