Construction updates from Market & Johnson…
Work performed in the last 5 days
- Started Abatement
- Started to Salvage Wood Paneling on 2nd Floor
- Started to Demo 1st and 2nd Floor Casework
- Started to Demo 1st Floor Carpet Tile
- Started to Demo Electrical Outlets and Lights
- Set up Temporary Power
- Continue to Work Through Shop Drawings/Submittals
Work scheduled for the next 5 days
- Continue Abatement
- Continue to Salvage Wood Paneling on 2nd Floor
- Continue to Demo 1st and 2nd Floor Casework
- Continue to Demo 1st Floor Carpet Tile
- Continue to Demo Lights
- Start to Demo HVAC
- Continue to Work Through Shop Drawings/Submittals