Construction updates from Market & Johnson…
Work performed in the last 30 days
- Mobilized to the Site
- Demoed Millwork
- Demoed and Recycled 12,000 SF of Second Floor Carpet
- Demoed Second Floor Lights
- Demoed Second Floor Ceiling
- Demoed Second Floor Plumbing
- Demoed Second Floor HVAC
- Salvaged 1,400 SF of Wood Paneling for Reuse
- Demoed and Recycled 18,000 SF of First Floor Carpet
- Demoed and Recycled 15 tons of Metal
- Demoed Front Entry Trees and Benches
- Continued Working Through Shop Drawing and Submittals
Work scheduled for the next 30 days
- Demo 2nd Floor Walls
- Demo First Floor and Lower-Level Plumbing
- Demo First/Second Floor Staircase
- Demo First Floor HVAC
- Demo First Floor and Lower-Level Lights
- Demo First Floor and Lower-Level Ceiling
- Demo First Floor Electrical Wall-ins
- Demo First Floor Walls
- Start Site Work
- Continued Working Through Shop Drawing and Submittals
- Coordinate Eau Claire Street Shutdown with U.S. Bank
Schedule
Demo Complete … July 30, 2021
Structural Steel Install … August 16, 2021
Occupancy Inspection … July 1, 2022
Photos by Market & Johnson (June)

Main Entrance with existing trees removed. 
Lower Level mechanical equipment removal in progress. 
Second Floor demolition progress. 
First Floor demolition progress at future Headwaters Area.