Work performed in the last 30 days
- Completed Abatement
- Demoed 2nd Floor Walls
- Completed 2nd Floor Demo
- X-Ray for PT Tendons on 2nd Level
- Installed Scaffold Work Platform at Headwaters
- Demoed 1st Floor and Lower-Level Plumbing
- Demoed 1st Floor HVAC and Lower-Level Lights
- Demoed 1st Floor and Lower-Level Ceiling
- Demoed 1st Floor Electrical Wall-ins and Walls
- Demo Lower Level Ceilings and Lower Level Lights
- Coordinated with City of Eau Claire and US Bank on Geo-Well Install
- Surveyed Geo-Well Locations
- Continued to Work Through Shop Drawings and Submittals
Facts
- Demoed and Recycled 40 Tons of Metal
- Demoed 90 Tons of Demolition Material
- Demoed and Recycled 25 Tons of Masonry Demo
Work scheduled for the next 30 days
- Demo Lower-Level HVAC and Walls
- Complete All Floors Wall Layout
- Continue X-Raying existing structure as needed.
- Begin Framing Walls 2nd Level.
- Demo Existing Elevator and Dumb Waiter
- Demo Roof and Parapet Walls for 3rd floor Addition
- Demo Structures at Existing 2nd Floor Room
- Demo and Prep New Masonry for New Openings
- Start Lower-Level Underground Plumbing
- Begin Site Work and Utilities
- Prep for Geo-Thermal Well Installation
- Continue to Work Through Shop Drawings and Submittals
Schedule
Demo Complete … July 30, 2021
Structural Steel Install … August 16, 2021
Occupancy Inspection … July 1, 2022
Photos by Market & Johnson (July)

2nd Level demo wrapping up, scaffold in place at Headwaters Area. 
1st Level demo near complete, stairway removal next. 
Lower Level demo in progress, wall removal upcoming. 
Existing rooftop air handler removed.